พฤษภาคม 2559 (Trackwork)

- Survey Track Measurement (No.216) at Mainline, Track (NB) CH:0+200.409 to CH:0+301.495

- Pouring Concrete (No.216) at Mainline, Track (NB) CH:0+200.409 to CH:0+301.495

- Survey Track Measurement before Casting Concrete Slab Track (No.78) at Depot, Track (WS-03) CH:0+002.505 to CH:0+008.604

- Slump Test Concrete Slab Track (No.78) at Depot, Track (WS-03) CH:0+002.505 to CH:0+008.604
(WS-04) CH:0+039.000 to CH:0+045.591

- Casting Concrete Slab Track  (No.78)  at Depot, Track (WS-03) CH:0+002.505 to CH:0+008.604
(WS-04) CH:0+039.000 to CH:0+045.591

- Curing Concrete Slab Track (No.78) at Depot, Track (WS-03) CH:0+002.505 to CH:0+008.604
(WS-04) CH:0+039.000 to CH:0+045.591

- Bracket Bolt for Conductor Rail before Casting Concrete Slab Track (No.78) at Depot, Track (WS-03) CH:0+002.505 to CH:0+008.604
(WS-04) CH:0+039.000 to CH:0+045.591

- ALUMINOTHERMIC WELDING T/O DP No 2019 (T-23) (WS04) CH:0+016.691 Total 2 joints and T/O DP No. 2061 (T-24) (WS04) CH:0+000.000 Total 2 joints

- De-Stressing at Depot, Track Line (PT) CH:0+306.009 to CH:0+675.989

- ALUMINOTHERMIC WELDING  at Depot, Track (PT) CH:0+470.048 WELD No . 0337 – 0338 (2 Joints)

- De-Stressing  at Depot, at Line Track (PT) CH:0+807.636 to CH:0+980.266

- ALUMINOTHERMIC WELDING at Depot, Track (T-29) T/O DP. NO. 2055  (WS03) CH:0+000.000  Total. 2 joint WELD NO. 0347 – 0348
(PT) CH:0+807.636 Total 2 joints  WELD NO. 0345 – 0346

-Survey Track Measurement (No.223) at Mainline, Track (NB) CH:0+599.710 to CH:0+699.890

- Pouring Concrete (No.223) at Mainline, Track (NB) CH:0+599.710 to CH:0+699.890

- Survey Track Measurement (No.225-1) at Mainline, Track (NB) CH:2+046.430 to CH:2+082.313

- ALUMINOTHERMIC WELDING  TO/DP. 2054. (T-28) at Depot, Track (SB-02) CH:0+034.056, (SB-01) CH:0+000.000, (CN2) CH:0+136.652, (Total 6 Joints)

- ALUMINOTHERMIC WELDING, TO/DP 2005 (T-22) at Depot, Track (PT) CH:0+155.557 Total 2 joint WELD NO. 0370 – 0369
(CN-3) CH:0+128.999 Total 2 joint WELD NO. 0368 – 0367

- Survey Track Measurement  (No.228) at Mainline, Track (EB) CH:0+809.656 to CH:0+847.131 (9 Slabs)

- GEOMETRY turnout 1/14 R300 at Mainline, To/ML/1012 (NB) CH:0+895.000 to CH:0+855.000

TO/ML/1011 (EB) CH:0+590.0000 to CH:0+557.000

- Pouring Concrete (No.228) at Mainline, Track (EB) CH:0+809.656 to CH:0+847.131 (9 Slabs)

(NB) CH:0+833.050 to CH:0+847.030 (4 Slabs) Turnout 1/14 R300 TO/ML/1011
51.455 M.

- Survey Track Alignment Platform at Mainline, at National Housing (E-23 )

- Electrical Testing  at Depot, Track (CN-3) CH:0+035.471 to CH:0+128.999

- Flash Butt Welding for Routine Test (2001st – 2500th) 6 Sample and Re-welding joint (No.03) (SH) (0-500th) 1 Sample

- UT & MT 6 Samples of Flash Butt Weld joints (2001st-2500th) and 1 Rewelding joint (SH) for joint (1st-500th)

- Survey Track Measurement (No.235) at Mainline, Track (EB) CH:1+069.746 to CH:1+190.945

- Pouring Concrete (No.235) at Mainline, Track (EB) CH:1+069.746 to CH:1+161.800

- De-Stressing at Depot, Track (WS-02) CH:0+063.714 to CH:0+120.00,(PT) CH:0+050.000 to CH:0+175.361

- Survey Track Measurement (No.236) at  Mainline, Track (EB) CH:1+162.106 to CH:1+247.870

- Pouring Concrete (No.236) at Mainline, Track (EB) CH:1+161.800 to CH:1+244.940
(20 Slabs/56 m^3)
 