มีนาคม 2559 (Trackwork)

- Inspection Rail De-Stressing at Depot, track SB-02,SB-03

- Inspection Alumino-Thermit Welding at Depot

- Inspection: Spacing Fastener before Casting Concrete Semi Embedded Track (No.6) at Depot, Track Semi Embedded (PW-2) CH:0+172.549 to CH:0+204.511

- Electrical testing Conductor Rail at Depot, Track SB01, SB02, SB03, SB04

- Witness Routine Test for Small Cable Tray (No.4) at Hicrete Factory Ayudhaya.

- Inspection Activity Pre-Assembly CDM –Q Track at Depot, Track at WM CH:0+167.000 to CH:0+172.000, Track PT CH:0+473.000 to CH:0+478.000

- Inspection Slow Bending Test for Flash Butt Welding Joint Routine Test No.1,001-1,500 at KMITT Lab

- Inspection Rail to Rail Insulation Resistance Test at Depot,  Track at WM CH:0+167.000 to CH:0+172.000,Track PT CH:0+473.000 to CH:0+478.000

- Inspection Running Rail/Turnout Continuity Test at Depot, Test Track (T-13) CH:0+400.000 to CH:0+750.000

- Inspection Track/Turnout to Earth Resistance Test at Depot, Test Track (T-13) CH:0+400.000 to CH:0+750.000

- Inspection Geometry T-32 1/6 R100 (RH) No.TO/DP/2001 and T-31 1/6 R100 (LH) No.TO/DP/2056 before Casting Concrete Slab Track (No.66)

- Inspection Spacing Sleeper and Bearers before Casting Concrete Slab Track (No.67)

- Inspection Bracket Bolt for Conductor Rail before  Casting Concrete Slab Track (No.70)

- Inspection Survey Track Measurement before Casting Concrete Slab Track (No.70)

- Inspection Slump Test before Casting Concrete Slab Track (No.70)

- Inspection Casting Concrete Slab Track (No.70) at Depot, Track (SB-02) CH:0+041.545 to CH:0+109.270

- Inspection Curing Concrete Slab Track (No.70) at Depot, Track (SB-02) CH:0+041.545 to CH:0+109.270

- Inspection Curing Concrete Slab Track (No.70) at Depot, Track (SB-02) CH:0+041.545 to CH:0+109.270

- Inspection STABLING TRACK SB-01 – 04 at Depot

- Inspection Survey Track Measurement (No.193) at Mainline, Track (NB) CH:3+468.304 to CH:3+532.269

- Radio Test for Routine Test of Flash Butt Welding Joint 1001 st-1500th   TINT

- Inspection Pull Out Test Shear Connector before Casting Concrete Slab Track (No.72) at Depot, Track Slab Track (WS-01)

- Inspection Spacing Sleeper before Casting Concrete Slab Track (No.72) at Depot, Track Slab Track (WS-01)

- Inspection Sccc Continuty Test Concrete Slab Track (No.72) at Depot, Track Slab Track (WS-01)

- Inspection Electrical Resistivity Test Shear Connector Concrete Slab Track (No.72) at Depot, Track Slab Track (WS-01)

- Inspection Final Inspection for Pouring (No.196) at Mainline, Track (EB) CH.3+569.694 to CH:3+642.261

- Inspection Survey Track Measurement (No.196) at Mainline, Track (EB) CH:3+642.261 to CH:3+569.694

- Inspection Pouring Concrete (No.196) at Mainline, Track (EB) CH:3+642.261 to CH:3+569.694

- Inspection ALUMINOTHERMIC WELDING at Depot, TO/DP/NO 2058 LH (T-30) CH.0+047.106

- Inspection Survey Track Measurement (No.198) at Mainline, Track (NB) CH:3+607.950 to CH:3+684.634

- Inspection Pouring Concrete (No.198) at Mainline, Track (NB) CH:3+607.950 to CH:3+675.460