กันยายน 2558 (Trackwork)

- Survey Track Measurement (No.64) at Mainline, Track (NB) CH.6+191.898 to CH.6+250.638

- Check Bracket before Pre Concretin at Mainline, Track (NB) CH.6+250.638 – CH.6+191.898

- Spacing Fastening Semi Embedded Track  (Pre- Concreting No.05) at  Depot, Track (WS07) CH.0+248.000 – CH.0+315.000

- Survey Track Measurement Semi Embedded Track (Pre- Concreting No.05) at Depot, Track (WS07) CH.0+248.606   to CH.0+315.675 

- SCCC Continuity Test before Casting Concrete Slab Track (No.33) at Depot, Track (WS01, WS03,WS05),(T-15 Turnout TG 1/6 R100 (RH)) No. TO/DP/2007,T-16 Turnout TG 1/6 R100 (LH)) No. TO/DP/2051)

- Survey Track Measurement (No.64) at Mainline, Track (NB)  CH.6+191.898 – CH.6+250.638

- Pouring Concrete (No.64) at Mainline, Track(NB) CH6+250.638 – CH.6+191.898

- Geometry Crossover Turnouts TG 1/14 R300 at Mainline, Track (EB) CH.6+425.000 – CH.6+475.000, (NB) CH.6+453.400 – CH.6+502.403, (TO/ML/1007  TO/ML/1008  RH )

- Survey Track Measurement (No.65) at Mainline, Track Crossover Turnout 1:14 R300 (RH) 1007,1008 (NB) CH.6+451.643 – CH.6+463.041 = 11.398 m.

(EB) CH.6+412.109 – CH.6+460.375 = 48.266 m.

- Bracket Bolt For Conductor Rail before Casting Concrete Slab Track (No.33) at Depot, Track (WS01, WS03, WS05) (T-15 Turnout TG 1/6 R100 (RH)) No. TO/DP/2007,(T-16 Turnout TG 1/6 R100 (LH)) No. TO/DP/2051

 